Phase 3
On September 14, 2021 the Department of Public Works sent Requests for Proposal (RFP) to Alcorn Fence Company and Surface Constructors. The project was also posted to BlueBook.com and emailed to an additional 15 contractors. All bids were due October 5, 2021 by 2 p.m. Alcorn Fence was the only bid received.
The 2021/22 fiscal year budget line item for guardrail repair allocates $75,000 to the project. Alcorn's bid came in $10,729 below the budgeted amount. The contract was awarded in October 2021.
Locations include:
- Deertrail near Paramount intersection
- Deertrail back side
- Deertrail north of Greenwater
- Deertrail near Starland
Work began on November 8, 2021 and was completed within 1 week.
Share Phase 3 on Facebook
Share Phase 3 on Twitter
Share Phase 3 on Linkedin
Email Phase 3 link
Project is complete